BAYDA April 25. 2024 (Saba) - The governor of Al Bayda reviewed the progress of work on the Southern al-Daery Road Project in Dhi Na’im District, at a cost of 13 million riyals.
The Governor heard, from the Director of the Executive Unit for Projects, an explanation about the progress of the surveying and backfilling work along a kilometer, and the completion rate, which reached 60 percent.